SQL doesn't always like having the server rename after SQL has been installed. I would install SQL after your rename the server.

 

Both SQL and Windows upgrade are fro the most part a "next, next,next" type of thing.

 

Some might argue that a side-by-side is more work but it will also be the safest. so what is the most important factors for you?

Share this post


Link to post
Share on other sites

Can't express how much of a help it has been to be able to bounce some ideas off of you guys. I'll be moving forward with the side-by-side migration and will update this thread along the way with any success/failures I've had.

Thanks again!

Cheers,

Greg

Share this post


Link to post
Share on other sites

I'm not sure why you're not considering doing a side-by-side migration. It's the best and most simple option for you. There are so much content on how to do it out there.

Hi NickolajA,
We are on the process of upgrading the server OS of an SCCM primary site and wanted to ask you what is the best way to approach this. We currently have SCCM 2012 R2 RTM running on a Windows Server 2008 R2. On the SQL side, the DB runs on SQL 2008 on a separate Win2008R2 server. Our goal is to bring a new Windows 2012 R2 server, install a new SCCM site and use the migrate feature.
Do you have any recommendations/suggestions?

Share this post


Link to post
Share on other sites

 

Hi NickolajA,
We are on the process of upgrading the server OS of an SCCM primary site and wanted to ask you what is the best way to approach this. We currently have SCCM 2012 R2 RTM running on a Windows Server 2008 R2. On the SQL side, the DB runs on SQL 2008 on a separate Win2008R2 server. Our goal is to bring a new Windows 2012 R2 server, install a new SCCM site and use the migrate feature.
Do you have any recommendations/suggestions?

 

 

What do you mean by migrate feature?

 

BTW, I would install SQL local to CM12. A ton less headache and generally better performance.

Share this post


Link to post
Share on other sites

So I've done this before a few times in lab and once in production. What I found was that I had to make some final "tweaks" to things like re-installing SUP upon restore and a few other roles including my MP role. Total down time for the system was about 2 days while I worked out the kinks in everything.

 

I have to go through the transition next year though once my server is up from its warranty and lease which I'm not looking forward to again.

 

We are also going UCS so my system will most likely end up with SQL on the cluster and my system as one of many VM's on our UCS setup. Thanks to all the great information on here though I believe I can hopefully get through this ok without to many headaches (SQL being the big one that is going to arise).

Share this post


Link to post
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

Loading...


×
×
  • Create New...

Important Information

We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.